Hawai'i’s 100% clean energy future 

As Hawai'i accelerates its transition to a 100% renewable future by 2045, AES Hawai'i is partnering with utilities, communities, landowners and customers to deliver greener, smarter energy solutions and help ensure a responsible and equitable transformation to clean energy. Since the 1980s, our people have worked passionately to meet Hawai'i’s growing energy needs. Working together, we are co-creating solutions that support Hawai'i’s renewable generation goals, stabilize rates and increase reliability.

Community meeting

30-day Public Comment Period: August 27 - September 26, 2024.

On August 27, 2024, a virtual community meeting was held for area residents and interested parties to learn more about Kūihelani Solar Phase 2, a proposed utility-scale solar project located in Central Maui. AES team members provided an overview of the Project, answered questions and gathered feedback. You can watch a recording of the meeting below:

Contact us

We appreciate your interest and participation in Hawai'i's renewable energy future. We look forward to hearing your ideas and comments.

Community Outreach Representative:
Carrice Gardner 
Email: kuihelani2solar@aes.com
Project Hotline: +1 (808) 800-3942 

AES Hawaiʻi is deeply committed to being an active, invested member of the communities we serve. 

 

Image
rectangle_32


AES Hawaiʻi has a track record of successfully and sensitively engaging with the community and stakeholders in the vicinity of the proposed project. 

Continuing to identify communities and other interested stakeholders affected by the project is an essential part of project planning. Upon award, the AES Hawaiʻi team will engage area organizations and leaders to provide timely and relevant project information and collect feedback to refine and finalize the project’s design with community input. 

We intend to make every effort to keep the following list up to date throughout the Project’s lifecycle. Preliminarily, AES Hawaiʻi has identified the following organizations, community leaders, and key decision-makers that will be engaged in the project outreach process:

  • Waikapū Community Association 
  • Alliance of Maui Community Associations
  • Area Council member Tasha Kama
  • Area Council member Alice Lee 
  • Senator Troy N. Hashimoto 
  • Maui Chamber of Commerce
  • Maui Economic Development Board
  • Maui Economic Opportunity
  • Maui Lani Community Association
  • Mahi Pono
  • The Living Pono Project LLC
  • Puʻu Kukui Watershed"

In addition, AES Hawaiʻiʻs standard practice is to ask these stakeholders to help identify others that should be contacted to continually expand its outreach.

 

Comprehensive communications plan

A significant goal of AES Hawaiʻi's Community Outreach Plan is to inform stakeholders and neighboring communities about the Project and its progress and collect their feedback. AES Hawaiʻi will build upon our previous experience to provide timely updates through a detailed community outreach schedule. AES Hawaiʻi is committed to sharing important information about projects in advance of any community meetings. Specific tactics to share information and gather input will include, but are not limited to: 

  • Issuance of Public Community Meeting Notice(s)
  • Conducting Public Community Meeting(s)
  • Conducting strategic outreach to area organizations, community leaders, and elected officials
  • Dedicated email address (kuihelani2solar@aes.com) to gather input, comments, and questions
  • Dedicated Project phone number (+1 (808) 800-3942)
  • Construction and status updates will be posted on the Project website (https://www.aes-hawaii.com/hawaii/project/kuihelani-solar-phase-2)
  • Issuance of monthly project status updates to our project mailing list; and
  • Public Community Meeting Summary.
Our community engagement process will:

Inform stakeholders and neighboring communities of the Project by communicating potential environmental, social, economic, and land use changes, and answer their questions. 

AES Hawaiʻi will continue to plan for either in-person or virtual community meetings based on public health and safety conditions at the time. To support community awareness of meetings, AES Hawaiʻi will issue media advisories a minimum of 30 days prior to a public meeting to Maui and statewide media, including but not limited to:  Maui News, Maui Now, Civil Beat, Hawaii News Now, KHON2 News, and KITV4 News. Additionally, we will advertise in area community publications and provide email notifications to stakeholders and those who have signed up to be on our project mailing list. 

Public comments in support of and in opposition to the proposed Project will be compiled and filed with the Public Utilities Commission.

AES Hawaiʻi believes in the importance of maintaining community collaboration and consultation throughout the project lifecycle and has successfully implemented this strategy with Hawaiian Electric Company's RFP Phase 1 & 2 projects. Throughout this process, collecting, considering, and responding to feedback from the stakeholders and neighboring communities enabled AES Hawaiʻi to garner support and tailor each Project to address and mitigate community-identified issues or concerns.

One of the earliest steps we take when undertaking a new project is to engage area community leaders, elected officials, residents, key government and industry organizations, and businesses. This approach enables AES Hawaiʻi to share information about a given project, build support and identify issues of concern so that we may respond to feedback from stakeholders and neighboring communities and develop mitigation measures. 

As an initial step in the strategic community outreach process, AES Hawaiʻi has conducted a survey of residents in Central Maui to gauge community sentiments and identify issues of importance. 

Construction Related updates

AES Hawaiʻi is committed to providing project status updates via email to our project mailing list,  at least once per month and in conjunction with key milestones to ensure community members and stakeholders have the opportunity to provide public comment as required by the RFP. 

Local Labor Partnerships

AES Hawaiʻi has a history of working with local labor organizations, including:

  • Hawaiʻi Carpenters Union
  • International Brotherhood of Electrical Workers, Local 1186 
  • Hawaiʻi Laborers Union, Local 368

  • Hawaiʻi Operating Engineers, Local 3

AES Hawaiʻi is deeply committed to maintaining these partnerships and providing opportunities for local residents to work in the renewable energy industry.

 

Local community support or opposition

AES Hawaiʻi has already conducted early-stage outreach by commissioning a public opinion survey to understand community sentiment regarding the proposed Project.

The public opinion poll provides initial documentation of the community’s support for the Project. Of the Maui residents who responded to our survey, the majority (70%) said they would support a solar and battery storage project capable of powering the equivalent of 17,500 homes sited on approximately 400 acres in Central Maui. The majority of residents who supported the Project cited that it would be good for the environment or climate and would reduce the cost of electricity. Similarly, more than half support it because it would help to cut down on fossil fuel use. Other key reasons for support of the Project include the understanding that it would create new jobs and be good for the community and the economy. These results will help shape our strategy for communicating the Project’s overall benefits.

During our ongoing community engagement process, AES Hawaiʻi will directly engage and listen carefully to community feedback regarding the Project. Project support and opposition will be identified through this process, along with community-identified concerns about project design, location, and potential impacts.  

Image
TKO_9304.jpeg

Community outreach efforts 

Image
img05.jpeg

As mentioned above, AES Hawaiʻi commissioned a public opinion to proactively seek early-stage community feedback and de-risk this Project. The confidential survey includes responses from 359 residents in Central Maui communities and gauges their level of support or opposition to this potential solar plus battery project sited on approximately 400 acres of land in Central Maui between Kūihelani Highway and Maui Veterans Highway in Kīhei.

In addition to the survey, AES Hawaiʻi will continue to host community meetings and meet with key leaders to provide opportunities for project feedback. The project website and dedicated email address will provide an additional venue to gather input, and answer their questions.

Community benefits

An early-stage community consultation occurred through a survey of Central Maui residents. The survey provided insights into the type of community benefits Central Maui residents value most. These findings are the first step in soliciting feedback and understanding the community-identified needs of Central Maui. 

As community engagement continues for this project, AES Hawaiʻi will seek further guidance from stakeholders on appropriate benefits the community would support. The project website and dedicated email address will be another venue for us to gather input from the host community.

Annual Community Benefits Commitment

AES Hawaiʻi commits to setting aside a minimum of $3,000 per MW AC per year for community benefits aimed at addressing specific needs identified by the Host Community or to a 501 (c)(3) non-profit community-based organization(s) to address Host Community-identified needs. 

AES Hawaiʻi understands that each community in Hawaiʻi is unique with different concerns and different needs. Our early-stage outreach is our initial effort to understand these concerns and needs and will inform future engagement. As part of the initial community meeting and continued engagement with the host community throughout every stage of the Project, AES Hawaiʻi will consult and solicit feedback and guidance from the community on where these funds are needed the most. This feedback will serve as the foundation of the Community Benefits Package for this Project and ensure it is specifically tailored to address the host community-identified needs.

Additional Community Benefits

Additional Project benefits and impacts were assessed through the commissioning of a preliminary economic and fiscal analysis. The analysis performed was based on preliminary project schedules, preliminary conceptual design and in constant 2023 dollars. 

1. Project construction will result in economic output benefiting Hawai‘i's economy.

  • The Project is anticipated to create approximately 1,400 direct, indirect and induced jobs.

  • The Project is anticipated to generate approximately $228 million in direct, indirect and induced economic activity.

2. Local Labor & Prevailing Wage

  • AES Hawai'i has existing partnerships with local unions and a proven track record of generating meaningful local employment opportunities with living wages.

  • Construction will create direct, indirect and induced jobs that benefit the local labor market

3. The Project is anticipated to reduce environmental impacts and increase energy resilience with local renewable power production.

  • Anticipated to generate approximately ~10% of Maui's energy needs.*

  • Upon completion, the Project is estimated to power the equivalent of 18,425 homes with clean, renewable energy annually.*

  • The Project is expected to prevent the consumption of more than 4.3 million barrels of oil over its 25-year lifespan.*

4. The Project provides fixed, low-cost, reliable renewable energy pricing compared to the fluctuating cost of fossil fuels. 

5. The Project helps to support the phasing out of traditional fossil fuel plants and grid modernization.

6. The energy produced from this Project will help the state achieve its goal of 100% renewable energy generation by 2045 and offset Hawaiʻi’s reliance on price-volatile, imported fossil fuel.

As predevelopment of the Project proceeds, additional opportunities for benefits will be explored in direct collaboration with the area communities. 

 

Community meetings and presentations

September 9, 2024 Waikapū Community Association Meeting

Presentation:  9.9.24 Kūihelani Solar Ph2 Waikapu Community Assoc. Presentation.pdf

 

Project benefits

Low and stable electricity cost

Under a Power Purchase Agreement (PPA) approved by the Public Utilities Commission (PUC), the Project will deliver power at a fixed price over 25 years. The low, stable pricing helps protect against volatile fossil fuel prices.

~10% of the island’s energy needs

Upon completion, the Project is anticipated to power the equivalent of 18,425 homes and generate approximately 10% of Maui's energy needs.*

4.3 million barrels of oil

The Project is expected to result in total avoided fuel consumption of 4.3 million barrels of oil over its 25-year span.*

1,400 jobs and $228 million in economic output

The Project is anticipated to create approximately 1,400 local jobs and generate an economic output of approximately $228 million

Project summary

Kūihelani Solar Phase 2 is a proposed 40 MWac solar photo-voltaic array and 160 MWh containerized lithium-ion Battery Energy Storage System (BESS) project to be developed and operated by AES Hawai‘i.

The project is located in Central Maui, approximately 5 miles south of Kahului, on land owned by Mahi Pono. As the design of the project has progressed and is informed by studies of the land, the following areas have been established:

  • Specifications: 40 MWac solar photovoltaic array plus 160 MWh containerized lithium-ion Battery Energy Storage System (BESS).
  • Power-Purchase Agreement: The project will deliver power to serve Maui residents under a 25-year Power Purchase Agreement with Hawaiian Electric at a low, fixed cost over that timespan.
  • Decommissioning: AES Hawaiʻi will restore the land to its existing condition (or comparable) at the end of the project’s life, consistent with the land agreement with Mahi Pono.
  • Project Study Area: AES Hawai‘i studied roughly 730 acres to responsibly site the Project Area, avoid sensitive features, and minimize potential impacts.
  • Preliminary Project Area: The project will be sited within a Preliminary Project Area of approximately 575 acres, all of which is within the Project Study Area. This will be further refined into the final Project Permit Area, which AES Hawaii anticipates will be reduced in overall size.
  • Preliminary Project Footprint: Solar panels, batteries, substation, and other project components are anticipated to occupy an area of approximately 250 acres, or approximately 34% of the total Project Study Area.

Project Name

Kuihelani Solar Phase 2, LLC

Owner

The AES Corporation

Project Capacity (MW)

40 MW AC

Proposed Facility Location

Central Maui

TMK(s) of Facility Location

TMK: (2) 3-8-005-002

Point of Interconnection’s Circuit

  1. MPP-Waena 69kV
  2. MPP-Waiinu 69kV

Project site maps

 

Project vicinity map

Preliminary Project area

Preliminary Project layout

Project schedule

The proposed timeline for project development and execution is included below. Please note: this schedule is subject to change and will be updated as necessary.

Environmental Permits and Approvals Strategy
  • Perform extensive due diligence on the site;
  • Identify community organizations, area leaders and key stakeholders;
  • Engage early and often with aforementioned individuals and organizations to share information and gather feedback; and
  • Proactively consult with resource and permitting agencies.

 

Activity
Status

Initial Community Assessment and Outreach

Initial community outreach and early-stage sentiment survey completed; community outreach and engagement will continue throughout Project development 

Permit Assessment

The assessment of permits and the required land use approvals needed is complete

Title and Easement Review

Ongoing

Archaeological Resources

Literature Review and Field Investigation (LRFI) completed. An Archaeological Inventory Survey (AIS) is in process

Cultural Resources

Preliminary assessment completed; in‐depth Cultural Impact Assessment (CIA) is in process

Biological Resources

Desktop assessment completed; Field surveys and consultation with USFWS and DOFAW in process

Waters of the U.S. Delineation and Jurisdictional Determination

Field surveys completed; consultation with USACE in process

Phase I Environmental Site Assessment (ESA)

Phase I ESA completed 

Geotechnical, Soil, and Hydrological Investigation

 Desktop geotechnical assessment (inclusive of site visits and consultation with local civil/geotechnical firms) completed; Full geotechnical and soils investigation completed with further investigations to be conducted throughout design; preliminary hydrological investigation and study complete

Visual Resources

Preliminary visual simulations and Glint/Glare assessment completed

Traffic Impact Assessment

A Traffic Impact Analysis Report (TIAR) is in process. Mitigation will be implemented during the construction phase of the project. Once operational and for the duration of the project, it is anticipated there will be minimal new traffic generation

Complementary Agricultural Uses

Preliminary agricultural assessment in development; to be refined 

 

Image
rectangle_7

 

Image
Cameron_at_Lawai.jpg

Based on these land use and zoning designations, the proposed solar and energy storage facility is a permitted use. No changes in the land use district or zoning classification are expected to be required for Project implementation.

Image
img10.jpeg

State Land Use District:

Agriculture

Land Study Bureau Soil Classification:

Classes B, C and E

HRS Chapter 205 Important Agricultural Land Designation:

Approximately 85 percent of the Project area designated as IAL (A&B 2009) 

Maui County Zoning District

Agricultural (approximately 95 percent), Open Space/Zone and Road (approximately 5 percent)

Maui Island Plan Designation

Outside Directed Growth Boundary

Kīhei-Mākena/South Maui Community Plan

Agriculture and Open Space 

Special Management Area (SMA)

100% of the Project area is located outside of the SMA

 

Based on a preliminary review, the following determinations have been made:


U.S. Federal

  • Filing of notice with the Federal Aviation Administration (FAA)

Maui County

  • County Special Use Permit(s) (CUP) from Planning Commission

  • Building Permit

  • Grading and Grubbing Permit

State of Hawaii

  • State Special Use Permit from Land Use Commission

  • Chapter 6E Compliance (Historic Preservation Review) by the State Historic Preservation Division

  • Certain construction-related State permits may be required, including:

    • National Pollutant Discharge Elimination System (NPDES) Permit

    • Noise Permit

 

Listing of anticipated Permits and Approvals

Anticipated Permit/Approval
Authority Having Jurisdiction

State Special Use Permit (SUP) 

Maui County Planning Commission and State Land Use Commission 

County Special Use Permit (CUP) 

Maui County Planning Commission 

HRS Chapter 6E Compliance (Historic Preservation Review) 

State Historic Preservation Division (SHPD) 

National Pollutant Discharge Elimination System (NPDES) Permit 

State of Hawaiʻi Department of Health (DOH), Clean Water Branch 

Noise Permit

DOH, Indoor and Radiological Health Branch

Building Permit

County of Maui Department of Public Works

Grading and Grubbing Permit 

Maui County Department of Public 
Works 

Filing of Notice 

Federal Aviation Administration (FAA) 

AES Hawai'i and its environmental consultant conducted a preliminary assessment of the environmental conditions at the site based on a review of publicly available maps, studies and previous environmental reports prepared for the property. More detailed information is being obtained through the due diligence and site-specific studies, as well as community feedback, and will be used to inform the design process.

The Project design will seek to avoid and minimize environmental impacts to the extent possible. Best Management Practices (BMPs) will be implemented to further minimize impacts throughout the Project lifecycle.

Feedback will be collected throughout the Project lifecycle, and updates will be provided as outlined in the Community Outreach section. To get the latest project information sign up to be placed on our mailing list.

Natural environment

 

Air Quality:
None of the equipment associated with the solar arrays or battery storage system emit air pollutants of any kind. Overall, the Project would provide a net benefit by replacing energy generated by burning fossil fuels with renewable energy, thereby reducing emissions of greenhouse gases.

Biology:
A site‐specific biological survey would be conducted as part of the detailed due diligence effort and the results would be incorporated into the planning and design process; if any sensitive biological resources are identified during this survey, the appropriate steps will be taken to avoid, minimize and mitigate potential impacts. 
 

Natural Habitats and Ecosystems:
Based on available information, the Project area has been highly disturbed by past land uses, which has presumably reduced the number and abundance of native species. Data from a statewide habitat assessment by USGS characterize the Project area as predominately heavily disturbed habitat consisting of cultivated agriculture, intersected by areas of low-intensity development (e.g., roadways) and scattered patches of native/alien mix habitat comprised of alien dry grassland and alien dry forest. 

According to publicly available data from the NWI (USFWS 2022a), NHD (USGS 2022), and DAR dataset (DAR 2008), the Project area contains several water features. Both Pale‘a‘ahu Gulch and Waikapū Stream run from northwest to southeast through the central portion of the Project area. NHD and NWI data identify Pale‘a‘ahu Gulch as an intermittent stream that connects to Keālia Pond; DAR classifies Pale‘a‘ahu Gulch as a non-perennial stream that terminates in the central portion of the Project area. Waikapū Stream is perennial, with continuous flow present throughout the year. Pōhākea Gulch flanks the western side of the Project area. A group of freshwater wetlands identified by NWI are located near the southern

boundary of the Project area surrounding Keālia Pond. In addition, several ditches are present, including Waiheʻe Ditch which runs along the northern edge of the Project area. The location of these features would be confirmed through a field assessment and the jurisdictional status would be verified with the U.S. Army Corps of Engineers (USACE). The Project would be designed to avoid discharge to any jurisdictional features such that no impacts to aquatic habitats are anticipated.

Climate:
The Project would generate clean renewable energy that would replace the burning of fossil fuel for the production of electricity, thus offsetting greenhouse gas emissions and providing a beneficial impact on climate conditions. 
 

Soils:
Ground disturbance during construction would be primarily related to driving steel posts to support the racking system for the solar panels, trenching for placement of electrical wiring, and excavation for foundations for the battery storage units, substation and interconnection facilities. All equipment will be removed, and the site restored after the life of the project leaving the soils in the same condition prior to construction. 
 

Topography and Geology:  
Topographic surveys have been conducted to inform project design as well as to minimize ground disturbance to the greatest extent practicable. Project design will continue to be refined as additional site studies are conducted.

Land regulation

Land Uses:
There will be no long-term impacts to future uses for this land. After the life of the PV + BESS facility the land will be restored for future uses.
 

Flood and Tsunami Hazards:
The Project has been sited to ensure Project infrastructure is outside the Hawai‘i Tsunami Evacuation Zone, and the Hawai‘i Department of Land and Natural Resources flood map’s flood zones A, AE, AEF, AH, AO, VE based on the Federal Emergency Management Agency’s Digital Flood Insurance Rate Maps.  
 

Noise:
The Project is not anticipated to generate meaningful noise impacts when operational. However, AES Hawaiʻi still plans on performing a noise assessment and, if required, obtaining a noise permit for work during construction. 

Roadways and Traffic:
A Traffic Impact Analysis Report (TIAR) will be prepared and any required mitigation will be implemented during the construction phase of the project. Once operational and for the duration of the project, it is anticipated there will be minimal new traffic generation. 
 

Utilities:
This project is not expected to require any utilities during construction. 

Socio-economic characteristics

The site is currently vacant land with similar uses surrounding the Project site. AES Hawaiʻi utilized the State of Hawai‘i Department of Business, Economic Development & Tourism (DBEDT) Map of Electricity Burdens on Hawai'i Households by Census Tract to preliminarily assess the project’s location and distance from nearby residents and the energy burden (defined as percentage of gross household income spent on energy costs) of those closest communities. The site is located approximately 4.0 miles away from the nearest community with an average electricity burden of 2.70%. The site is located approximately 4.0 miles away from the nearest community with an average electricity burden of 2.70%.

According to the American Council for an Energy-Efficient Economy (ACEEE), the Median energy burden nationally is 3.1% and the median low-income energy burden is 8.1%, which puts this area at slightly above the national average for non-low-income households. According to the same source, a high energy burden is considered to be above 6% and a severe energy burden above 10%.

Aesthetic/visual resources

A visual impact analysis will be conducted. The Project will be designed to minimize visual impacts to the extent practicable.

Solid waste

The facility is not anticipated to generate solid waste.

Hazardous materials

A Phase 1 Environmental Site Assessment (ESA) was conducted for the site and it was confirmed that no recognized environmental conditions (RECs), historical RECs (HRECs), or controlled RECs (CRECs) have been reported within the subject property.

Water quality

A Waters of the U.S. Delineation and Jurisdictional Determination will be conducted prior to construction and any potential jurisdictional water feature would be avoided such that the Project would not result in discharge to Waters of the U.S. Maui County Wetland Ordinance study is in process, and preliminary setbacks have been incorporated into the Project’s design where applicable.

Public safety services (Police, Fire, Emergency Medical Services)

The project is located near dense population centers and has access to Public Safety Services.

Recreation

The project site does not host any recreation activities and will not impact future recreation activities.

Potential cumulative and secondary impacts

The Project would directly contribute to the state’s renewable energy goals and in doing so would directly contribute to replacing a portion of electricity that is currently generated by burning fossil fuels, thus reducing greenhouse gas emissions and other forms of pollution that are detrimental to the environment and human health.

 

AES Hawaiʻi is deeply committed to engaging with the community early and often throughout the project’s lifespan. 

AES Hawaiʻi takes the Archaeological and Cultural Resources review very seriously. As we have done for all Hawai‘i projects previously developed or currently in development, this project will undergo extensive Archaeological and Cultural reviews to gain a comprehensive understanding of the land and any potential impacts resulting from the proposed development. To the extent practicable, all steps will be taken to carefully record, avoid, and/or mitigate impacts to archeological and cultural resources. Past practices that may be utilized for this project include but are not limited to: hiring local on-island firms to perform an Archaeological Inventory Survey Report (AIS), Ka Pa'akai Analysis, Cultural Literature Review, Archeological Literature Review and Field Inspection Report and Cultural Impact Assessment (CIA). These initiatives will often include interviews and consultation with lineal and cultural descendants, kupuna, Native Hawaiian Organizations (NHOs), agencies and area cultural leaders, and presentations to interested groups and parties. 


AES Hawaiʻi has engaged a local archeological firm and cultural consultancy to conduct early-stage initial analysis that identifies: 

  • valued cultural, historical, or natural resources in the area in question, including the extent to which traditional and customary native Hawaiian rights are exercised in the area; 
  • the extent to which those resources – including traditional and customary native Hawaiian rights – will be affected or impaired by the proposed action; and 
  • the feasible action, if any, to be taken to reasonably protect any identified cultural, historical, or natural resources in the area in question, and the reasonable protection of traditional and customary native Hawaiian rights in the affected area. 

AES Hawaiʻi has also engaged the firm to perform an Archaeological Literature Review and Field Inspection Report (LRFI) for the proposed Project area. 

In addition, the firm will conduct a preliminary cultural review and Cultural Literature Review (CLR) to understand and anticipate potential cultural resource impacts.

LRFI Findings Summary

The LRFI investigation was conducted – through historical, cultural, and archaeological background research and field inspection of the Project area.

The results of the LRFI recommend an AIS be conducted. AES Hawaiʻi is in the process of conducting the AIS.

Ka Pa'akai Analysis

AES Hawaiʻi is committed to conducting a Ka Pa'akai Analysis. In addition, AES Hawaiʻi will consult with SHPD to determine whether a CIA is warranted based on the results of the CLR and Ka Pa'akai Analysis. 

* Subject to change based on further analysis.